The Building Process 

​

We can build on our lot or a lot you own; MBM can also find you a lot, fill out our contact form and let us know your home goals. MBM does new construction, renovation, and additions. Below is a general outline of the construction phases.

​

Planning & Foundation

2 Months

​

  • Architectural Planning

  • Engineering -Plans get Stamped

  • Permits (City says OK!)

  • Lot Graded

  • Footings

  • Foundation Built

  • Survey

  • Inspections

​

Framing & Roughins

3-4 Months

  • ​Framing

  • HVAC Roughin (Heatings,Ventalation & AC

  • Electrical Roughin

  • Plumbing Roughin

  • Inspections for Above

  • Selections- Cabinets,Counertops,Tile,Carpet,Hardware, PaintColors, Yes! now, need to keep schedule!

  • Drywall

  • Insulation

  • More Inspections

Trim Outs & Details 

1-2 Months

​

  • Trim Outs (HVAC,Electric,Plumbing...vents,lights up & bath fixutres in.

  • Siding/Masonry

  • Driveways & Sidewalks

  • Interior Trim

  • Cabinets Installed

  • Tile

  • Countertops in

  • Walls Painted

  • Inspections

Yard & Punch List 

1 month

  • Landscaping

  • Fence

  • Patio

  • Final Inspections

  • Certificate ofOccupancy (CO)

  • Move in your new MBM Home